Differences

Check changes to actual time separately from differences between planned and actual time.

Under Shifts → Discrepancies (Dienste → Abweichungen), there are two different lists. A request for a time correction and an existing difference between a planned and actual shift are different matters.

List What to check
Actual-time change requests (Ist-Zeit Änderungsansuchen) Previous actual time, requested new actual time, difference, comment, and decision status.
Planned / actual discrepancies (Plan / Ist Abweichungen) Differences between planned and actual times relating to a person and date.

Employees open the relevant shift under My roster (Mein Dienstplan) and use Change request (Änderungsansuchen) if offered. Check the date, start, and end. Add a traceable reason. Check the status after requesting. The change remains open until a decision is made.

  1. Select the period and, for change requests, the Requested (Angefragt) status.
  2. Open the specific entry. Compare the previous and requested time and the difference.
  3. Clarify the reason with the person concerned. Check effects on other entries and monthly confirmation.
  4. Use Approve (Genehmigen) or Refuse (Ablehnen) only with the intended permission. Afterwards, check the status and actual shift time.

Monthly confirmation can set open requests to Expired (Abgelaufen). Clarify a necessary correction before confirmation. A planned/actual difference alone is neither an open request nor an automatically accepted correction.